Director of public road company Putevi Srbije Zoran Drobnjak and Director of Austrian construction firm Strabag in Serbia Dragan Pavelic signed an Agreement on the reconstruction of Gazela bridge today.
Zoran Drobnjak, left, and Dragan Pavelic
Author:
Tanjug
Drobnjak said after signing the Agreement, whose value is €58 million, that the reconstruction of the bridge is likely to start next week and will be conducted in four phases over the next 22 months.
He said that the beginning of the reconstruction of the bridge will depend on weather conditions and added that the first phase will last until September this year.
Reconstruction of the E -75 section from Nikola Tesla Airport to the toll point at Bubanj Potok will begin this year on 5 April.
Construction will be financed with a €25 million loan from the European Bank for Reconstruction and Development and the contractor is the Porr and Teerag Asdag consortium, said Drobnjak.